Building Update
The new building will connect to the existing Foyer through what is now a men's restroom. There will still be a small single use restroom there, but there will be a 10-ft. wide corridor connecting the new Gathering Room to the existing foyer. To facilitate this two AC units had to be moved along with the associated electrical and a gas line had to be relocated. That work has been completed!
The building foot print has been laid out on the parking lot with orange paint, thanks to Robert Read and Ralph Yeager. When you get the opportunity take a look and walk it out to see the size and how it will align with the existing building.
Existing septic tanks that are located on the east side of the choir room just outside the parlor entrance door will have been moved south past the corner of the office building. All existing drain lines were extended to the new tanks and new sprinkler heads were added to the aerobic system.
Bids have been gathered for Phase 1 and construction has begun on the parking lot addition, which must be completed before starting the building foundation. Ready for first pour August 1, 2025.
Excavation of the building foundation will begin September 15, 2025, and We will begin using the new parking lot on Sunday September 21, 2025.
The entrance driveway for the parking addition was poured Tuesday September 9, 2025. Striping is scheduled for Monday September 15, 2025, and we plan to start using the new lot on Sunday September 21st.
Excavation for the building foundation was completed Monday October 6, 2025 and backfill with select fill was started the next day.
Installation of storm drains started October 31st, and drilling and pouring of piers started November 4th. Piers should be finished by November 14th at which time the plumber will start.
The slab was poured 12-22-25 and it looks great, see photos below
Connecting hallway and walkways were poured 1-3-26.
Asphalt being removed 1-6-26 preparing for new concrete paving in front of church. Hilltop Lakes Water boring under Hilltop Drive for new 2-inch water supply line to new building.
The metal building is scheduled to arrive the week of January18, 2026 and the contractor will start erecting immediately.
The major frame of the building is up and roof is being installed February 4, 2026
The front driveways, parking and sidewalks are now poured February 5, 2026, and will be usable by Sunday February 15, 2026.










